Depot report 22/4/25


55009 repaint nears completion. Photo Pete Stojanovic
55009 repaint nears completion. Photo Pete Stojanovic

Pete Stojanovic writes.


A good day at our depot saw more work in the stores. It’s good to see major progress on the reorganisation of them.


All of the fuel pumps were changed on power unit 417, No.2 end of Tulyar. Hopefully this will resolve the rough running of the power unit.

One of the faults from the test run last week, a sticking load regulator was repaired.


Painting continued with 55009 which is getting close to completion, with just No.1 nose end, cab and part of the roof to complete.


Power unit 430 is nearly reunited with its overhauled main generator, after it was placed on the splitting stands. Minor adjustments next week should see the generator bolted to the engine.

Refurbished main generator ready to be fitted to PU430. Photo Pete Stojanovic.
Refurbished main generator ready to be fitted to PU430. Photo Pete Stojanovic.
Refurbished fuel pumps fitted to B bank on PU417, #2 engine on D9015 Tulyar. Photo Pete Stojanovic.
Refurbished fuel pumps fitted to B bank on PU417, #2 engine on D9015 Tulyar. Photo Pete Stojanovic.
B bank fuel pumps removed from PU417 for cleaning and refurbishing. Photo Trevor Savage.
B bank fuel pumps removed from PU417 for cleaning and refurbishing. Photo Trevor Savage.

 
 
 